Construction Notice – Paving Improvement Districts 133 – Mill & Overlay
The mill & overlay work planned as part of Paving Improvement District Number 133 is tentatively scheduled to begin on Monday, September 28th. Following is a tentative schedule for the work, weather pending:
- Day 1: Milling Operation – Granger Addition
Pavement Removals, Excavation – 9th Ave SE – 6th St SE to 7th SE (Granger Add.) - Day 2: Excavation, Fabric, Aggregate Base – 9th Ave SE (Granger Add.)
Milling Operation – 4th Ave SW – Wintershow Rd to 4th St SW
Paving Operation – Granger Addition - Day 3: Milling Operation – Valley View Addition
Paving Operation – Granger Addition - Day 4: Paving Operation – Granger Addition & 4th Ave SW
- Day 5: Paving Operation – Valley View Addition
- Day 6: Paving Operation – Valley View Addition
No parking will be allowed on the street during either the milling or the paving operation. No parking signs will be placed by the contractor a minimum of 24 hours prior to beginning work in each neighborhood.
During the mill & overlay process, the roadway will remain open, but traffic will be delayed. The reconstruction of 9th Ave SE will require the closure of the roadway.
The seal coat work planned for Paving Improvement District 133 has been delayed for 2026 and will now be completed in 2027. Information regarding the start of that work will be provided next spring.
If you have any questions regarding the project, please contact Chad Petersen, KLJ at (701)845-4980.